Whilst respecting the principals of free speech, Riccall Parish Council expect comments to be decent and inoffensive to others. Any material which the Parish Council considers offensive or defamatory will be removed immediately. This may include all of the comments being removed from certain news stories.

A19 FULFORD ROADWORKS

Weeks 74 & 75 commencing Monday 6th November 2017 

 

This is the 38th edition of the newsletter that keeps you up to date with the progress of the Germany Beck junction works on the A19 in Fulford. 
During the past two weeks we have been continuing the brickwork walls to the retaining wall parapets and have commenced the foundation blocks to the boundary walls of the property adjacent to the A19.
Elsewhere we have been preparing for surfacing to recommence next week.
Works have been slow whilst we wait for the completion of the gas diversion on the A19. Once complete work will pick up pace again.
 

During the next 2 weeks we will be  - 

  • Continuing the brickwork boundary walls adjacent to the A19
  • Preparing carriageway and footpaths for surfacing.
  • Surfacing all available footpaths and carriageway to the spine road
  • Surfacing the footpaths on Fordlands Road
  • Fordlands Road ramps to be adjusted to the permanent gradient and traffic management removed.
  • Northern Gas will be continuing their diversion work in the A19 which may result in the intermitent use of traffic signals on the A19. 
  • Constructing public footpaths within the flood alleviation area
  • Constructing public parking area within Permission's development area.

The closure of the eastern footpath on the A19 remains in place. 

Back to all posts

Post a comment