Whilst respecting the principals of free speech, Riccall Parish Council expect comments to be decent and inoffensive to others. Any material which the Parish Council considers offensive or defamatory will be removed immediately. This may include all of the comments being removed from certain news stories.

WEEK 3 BARLBY ROUNDABOUT UPDATE

 

 

Barlby Roundabout Newsletter 03. Weeks 4 & 5 commencing 10th October 2016

 

This is the third edition of the newsletter that will keep you up to date with the progress of the roundabout construction on the existing A19/A163 Market Weighton Road junction and also changes to the existing York Road junction. 

Over the past couple of weeks we have been locating all the existing services e.g. water, gas and BT and excavating for the roundabout construction to the east of the A19.

During the next 2 weeks we will be importing stone for carriageway construction and commencing drainage connections and kerbs.

These works focus on the areas of the new roundabout that do not impinge on the current junction and therefore should have little affect on traffic. 

You will notice, however, road works signs and cones to protect our workforce and advise you of a temporary enforceable reduction in the speed limit of 60 mph to 40 mph, again to protect our workforce.
 

 

 